Norway’s parties push for temporary halt on new data centres

Five Norwegian parties back a temporary halt on new data centres as NVE warns demand could reach 25 TWh by 2035. A Storting debate is due this week.

DataCenters News

·

·

3–4 minutes
Water rushing from a hydropower dam and power station in Norway

A growing bloc of Norwegian parties is calling for a temporary halt on new data centre construction, with an urgent motion due before the Storting this week. The push follows fresh official warnings that the sector’s power demand could rise sharply on the back of grid connections already approved.

What happened

The far-left Red Party (Rødt) has said it will table an urgent proposal in parliament to stop the establishment of new data centres. According to Norwegian news agency NTB, the Socialist Left Party (SV), the Greens (MDG), the Christian Democrats (KrF) and the Centre Party (Sp) also support a temporary halt. The Progress Party (Frp) wants tighter control and a system for prioritising who receives electricity, while the Conservatives (Høyre) want stricter regulation. Similar proposals have been voted down before, and a majority would need the backing of either Frp or Labour, which leads a minority government.

On 2 November, SV MP Lars Haltbrekken set out a concrete mechanism, Aftenposten reported: a national planning provision under the Planning and Building Act that would pause new projects until national rules are in place. He compared it to the five-year halt on large out-of-town shopping centres that Norway introduced in 1999. Under his proposal, only data centres with a societally critical function would be exempt.

Digitalisation minister Torgeir Micaelsen has said the government must act quickly but also correctly, and is working on short- and long-term measures without giving a timetable. Energy minister Terje Aasland told Reuters the aim is “ensuring the right kind of data centre establishments in Norway”.

The key numbers

A government-commissioned report by Menon Economics, published on 29 October, found that data centre electricity use quadrupled in three years to 3.2 TWh in 2025, about 2.3% of national consumption. Direct value creation was NOK 3.2 billion, with around 600 people employed. Foreign owners account for about 94% of that value; Norwegian ownership is more common among smaller facilities.

The report’s scenarios put sector consumption at 17–37 TWh a year by 2035. Data centres already account for roughly half of the capacity reserved at grid operator Statnett and in its connection queue. Separately, energy regulator NVE has projected that demand could reach up to 25 TWh by 2035 based on connections already granted, against a hydropower system that normally runs a surplus of about 15 TWh.

Context: Nordic grids move away from first come, first served

Statnett currently allocates capacity largely on a first-come, first-served basis. Norway’s debate mirrors moves elsewhere in the region: Denmark approved a four-tier grid prioritisation model in October that places most data centres at the back of the queue, while Finland is pursuing a similar approach with more flexibility for smaller sites. Some Norwegian municipalities have begun setting their own allocation criteria, including community benefit.

Why it matters for modular and edge in Europe

Norway has been one of Europe’s most attractive locations for fast-built AI capacity, including factory-built and phased designs that rely on quick grid energisation. A blanket pause would hit those projects as hard as hyperscale campuses, since speed of construction offers little advantage if permits stop.

The detail of any exemption will matter. A carve-out for “societally critical” facilities, or criteria favouring local ownership, could leave room for small regional and edge sites serving public services, defence or domestic businesses. Developers of modular capacity in the Nordics should watch whether the final rules distinguish by size, function or flexibility, rather than treating all data centres as a single category.

Sources