·

Merlin pauses two Arasur data centre buildings over power supply

Merlin Properties pauses Arasur 4 and 5 data centre buildings in Álava after Basque rejection of Solaria solar parks left power supply uncertain.

·

·

2–4 minutes
Electricity transmission pylon against a cloudy evening sky

Spanish real estate group Merlin Properties has suspended work on two further data centre buildings at its Arasur campus in Álava, in the Basque Country, until it has firm guarantees of electricity supply. The pause follows the Basque Government’s refusal to authorise a series of solar parks that energy partner Solaria had planned to help power the site.

What happened

The buildings affected are Arasur 4 and 5, the next phase of Merlin’s campus at Rivabellosa, south of Bilbao and close to Vitoria. The decision was first reported by Economía Digital, confirmed by the regional outlet Crónica Vasca and later covered by DatacenterDynamics on 19 November.

Solaria was due to provide part of the electricity for both buildings from renewable generation. In July, however, the Basque department responsible for industry and energy transition rejected administrative authorisation for 19 solar parks Solaria had proposed in Álava, leaving the supply schedule in doubt.

Merlin chief executive Ismael Clemente has said the company will not go ahead with the buildings without sufficient power guarantees. According to DatacenterDynamics, Merlin is working with Solaria on options to move that consumption to other parts of Spain with more room for self-generation.

The key numbers

  • The two paused buildings represented about €1.7 billion of investment and around 480 jobs, according to Crónica Vasca.
  • Arasur already has one live 24MW building, with a second due before the end of the year and a third next year, DatacenterDynamics reported.
  • Merlin has reportedly estimated that adapting its portfolio to Spain’s proposed data centre rules would cost an extra €863 million, mainly for battery energy storage, or 11.3% on top of planned investment.

Context: a tougher power picture in Spain

The Basque setback comes as Spain finalises a royal decree on data centres, first proposed in late August. Draft versions require new facilities to cover a large share of their consumption with renewable power on an hourly basis, a requirement reported at 80%. Industry body Spain DC and several operators have questioned the framework.

This is not the first time power has reshaped Merlin’s plans. In February the company ruled out building in Andalusia for lack of firm supply. DatacenterDynamics also reported that its project at Navalmoral de la Mata in Cáceres, designed for up to 100MW of IT load in its first building, would initially run at just 2MW because of current grid limits. Merlin is reportedly considering shifting some capacity to Madrid, Portugal and a second site in Aragón.

Why it matters for modular and edge in Europe

The Arasur pause shows that firm power, rather than customer demand, is now setting the pace of many European projects. When a renewable supply plan depends on generation that has not yet been permitted, large single-phase buildings become hard to commit to.

That strengthens the case for designs that can be built in smaller, phased increments matched to the power actually available, and for prefabricated battery and power skids that can be added as rules on renewable matching tighten. Merlin’s reported reliance on battery storage to meet the draft decree suggests on-site storage is becoming a standard part of the specification in Spain, for large campuses and smaller facilities alike.

Sources


Discover more from DataCenters News

Subscribe to get the latest posts sent to your email.

Get DataCenters News by email

New stories on modular, containerised and edge data centres in Europe, straight to your inbox. No spam, unsubscribe at any time.

Leave a Reply