Algorithmic trading firm XTX Markets has opened the first data centre on its campus in Kajaani, central Finland, bringing 22.5MW of IT capacity under its own ownership. The company used the opening to warn that slow permitting for grid infrastructure could put later phases of the campus at risk.
What has opened
XTX announced the opening on 24 November. The first facility sits on a 193-hectare site, has 15,000 square metres of floor space and provides 22.5MW of IT power. A second data centre on the campus is scheduled to begin operating in 2027. The firm says it has hired more than 30 full-time staff in Kajaani, covering engineering, operations, security and maintenance, and that the site can accommodate 50 permanent employees.
Until now, XTX ran its machine-learning compute cluster in leased capacity at sites across Europe. Moving into its own building has involved a large migration. In one six-week stretch, the company says it relocated 417 petabytes of storage – 385 servers holding 17,000 drives and weighing 26 tonnes in total – from a leased facility around five kilometres away. XTX also says the new building uses no water for cooling.
The grid warning
According to the company, electricity supply and grid connections are in place for the first two facilities. Power for the third, which is already under construction and due to be completed in mid-2028, remains uncertain because of delays in government expropriation permits needed for grid development. XTX intends to add further facilities on an annual basis after that.
Chief operating officer Mike Irwin said the firm has invested more than €400m in construction so far and has ambitions to invest billions more, but criticised what he described as a lack of engagement from government on the expropriation process. “Expropriation permits that once took months can now take years,” he said. Irwin added that XTX was willing to contribute financially to infrastructure solutions, while stressing that long-term investment needs long-term certainty.
Data Phoenix reported that the link in question is a proposed 400kV transmission line connecting the campus to a substation in Otanmäki, which requires a permit to acquire rights along its route.
Context
XTX first set out its Kajaani plans in January 2025, when it said it would invest more than €1bn in a complex of five data centres and had begun construction on the first. At the time, the company said its compute needs had outgrown the leasing options available to it. Construction has relied almost entirely on Finnish contractors, with more than 400 people on site at peak. Alongside the opening, the firm announced philanthropic commitments of more than €1.6m for local community projects, education and data centre skills training.
Why it matters for modular and edge in Europe
The Kajaani opening shows that the buildings themselves are no longer the main bottleneck. A well-funded owner delivered its first hall on schedule, yet the timing of its third depends on a land-rights permit for a transmission line. That pattern is increasingly common across Europe, from Norway’s pause on new grid reservations to connection queues in the UK and Spain.
For suppliers of prefabricated and modular capacity, the practical implication is that speed of delivery only pays off where power is already secured. Projects that can be phased in blocks matched to confirmed connection capacity – rather than built ahead of uncertain grid upgrades – carry less risk of stranded investment. The case also illustrates a wider trend of compute-heavy firms leaving leased colocation for owned, air-cooled capacity in cooler Nordic locations.