The Walloon Region has ordered Google to stop construction at its data centre site in Farciennes, near Charleroi in Belgium, after inspectors found work continuing on a building whose amended permit had been revoked in August. The case, which centres on a plan to cool servers with river water, now heads to Belgium’s Council of State in January.
What happened
Regional officials inspected the site on Thursday 26 November and ordered work to stop, the Walloon administration confirmed on Friday. Around 300 construction workers were present when the order was given, a regional official told Belgian broadcaster VRT. Local reports describe the building concerned as covering roughly 30,000 square metres and close to completion.
The intervention followed an emergency procedure launched by Greenpeace Belgium on 25 November. Using satellite imagery, the group said construction had carried on for months after the permit change was annulled. Walloon infrastructure minister François Desquesnes had announced an investigation a day before the inspection.
The permit dispute
Google’s original permit, granted in 2024, covered three air-cooled data centres at the Ecopôle business park, which straddles Farciennes, Aiseau-Presles and Sambreville. According to Greenpeace, the company later revised the design, merging two buildings into one larger structure and switching to cooling with water drawn from the Sambre river.
The Walloon administration approved that amended permit in April 2026. After residents appealed, Desquesnes revoked it in August, following an unusually hot and dry summer. The request covered 600 cubic metres of river water per hour, with less than a quarter returned to the river, according to the Belga news agency.
Google asked the Council of State on 17 October to annul and suspend the minister’s decision. Greenpeace and several residents applied to join the case in November, and a public hearing is set for 7 January 2027. A Google spokesperson told VRT the company is committed to open dialogue with the regional government and experts. Greenpeace Belgium said that “tech giants are not above the law”.
Google has presented the Farciennes campus as an investment of around €1 billion. It already operates a large campus at Saint-Ghislain, about 30 minutes away.
Why it matters for modular and edge in Europe
The Farciennes halt is a hyperscale case, but its core issue is one every European developer now faces: water and cooling choices are becoming permit conditions, not engineering details. A design change from air to river-water cooling was enough to bring a near-finished building into dispute, and regional authorities have shown they are willing to enforce permits on site.
For modular and edge operators, the lesson cuts in two directions. Smaller, factory-built facilities using closed-loop liquid or air-based cooling typically draw far less water and may face lighter scrutiny, which can be a selling point with planners and communities. At the same time, prefabricated designs are often revised between permit and delivery as specifications change. Developers should treat any change to cooling, water use or building footprint as a potential permit amendment, and secure it before work proceeds rather than relying on an appeal.
The case also adds to a growing list of European projects slowed by environmental review, after Finnish authorities intervened at Google sites in October.
Sources
- Greenpeace Belgium: press release on the suspension of construction
- RTBF: Farciennes, Google continues works without adequate permit
- TNW: Belgium’s Wallonia halts Google data centre after permit was revoked
- Techzine: Regional authority halts Belgian Google data center construction
- DatacenterDynamics: Construction paused at Google data center in Farciennes, Belgium