Lisbon-based investment firm Fortitude Capital is developing Hermes, a 202MW greenfield data centre campus for artificial intelligence workloads in Sines, on Portugal’s Atlantic coast. The project would make Sines home to a second large AI campus alongside Start Campus’s SINES Data Campus.
What happened
Fortitude describes Hermes on its website as a greenfield campus designed for high-density AI and high-performance computing (HPC). The site is in the Sines Industrial and Logistics Zone (ZILS), which is managed by the state company AICEP Global Parques.
The project emerged in the same update in which AICEP Global Parques confirmed to the weekly Expresso that Iberdrola had withdrawn its Green Ammonia Express plan for the zone, as reported by ECO and The Portugal Brief on 23 November. DatacenterDynamics covered the Hermes plan on 26 November.
Key numbers
- Planned capacity: 202MW, according to Fortitude.
- Developer: Fortitude Capital, a private equity firm founded in 2022 by António Esteves and Mário Vigário. Hermes is its first move into digital infrastructure.
- Not yet disclosed: investment amount, construction timetable, licences or an environmental assessment.
- The withdrawn Iberdrola project had been budgeted at €426.8m and planned to produce about 95,000 tonnes of green ammonia a year on roughly 21 hectares of the zone.
Context: Sines as an AI hub
Sines already hosts Start Campus’s SINES Data Campus, which is permitted for up to 1.2GW of IT capacity across six buildings. Its first building, SIN01, is operating and uses seawater for cooling; a second building of around 200MW, SIN02, is planned next. On its own, Hermes would be roughly the size of SIN02.
The arrival of a data centre in place of a hydrogen project also reflects a wider shift. ECO has reported that Portugal’s pipeline of green hydrogen projects has thinned, with more cancelled, refused or lapsed than cleared to proceed. Meanwhile, the government has ordered the Directorate-General for Energy and Geology (DGEG) to draw up grid connection rules for data centres by 11 December.
Why it matters for modular and edge in Europe
Hermes is a large campus rather than an edge facility, but high-density AI builds of this kind increasingly rely on prefabricated power and cooling blocks, such as electrical skids and coolant distribution units, to shorten construction schedules. Portugal already has a growing local supply base for such equipment, including the modular data centre factory that CTS opened in Viana do Castelo this month.
The forthcoming national grid rules are equally relevant to smaller operators. How Portugal allocates connection capacity between gigawatt-scale campuses and smaller regional or edge sites will shape where modular capacity can be deployed in the country over the next few years.
Sources
- DatacenterDynamics – Fortitude Capital plans 202MW AI data center campus in Sines, Portugal
- The Portugal Brief – Iberdrola abandons green ammonia plan for Sines as AI data centre campus joins the zone
- Gleeds – SINES DC Building 02 (SIN02) project page
- DatacenterDynamics – CTS Group opens modular data center factory in Portugal