Welsh ministers call in gas-backed Cardiff East data centre plan

Welsh ministers have called in the Cardiff East data centre plan, which includes a 49.9MW temporary gas energy centre pending a grid connection.

·

·

2–4 minutes
Rows of server racks with network cabling inside a data centre

The Welsh Government has taken the decision on a proposed data centre at the Cardiff East Park and Ride site out of the hands of Cardiff Council. The scheme, which would rely on a temporary gas-fired energy centre until a grid connection is available, will now be determined by Welsh ministers.

What happened

A letter from the Welsh Government’s Local Government and Planning Directorate dated 11 November, reported by Nation.Cymru, said Cabinet Minister Siân Gwenllian had directed that the application be determined by Welsh ministers under section 77 of the Town and Country Planning Act 1990. Cardiff Council’s head of planning told councillors that the special planning committee meeting scheduled for 12 November, at which officers had recommended approval, would no longer take place.

According to the reported letter, ministers concluded that the proposal raises issues of more than local importance, including possible conflict with national policy on transport, energy and flood risk, the scale of its environmental effects and the level of controversy beyond the local area. A holding direction issued in August had already prevented the council from granting permission while the call-in request was considered. The call-in is a procedural step: the application has been neither approved nor refused.

The scheme in numbers

  • Applicant: Curtis Hall Ltd; hybrid application reference 26/00109/HYB.
  • Up to 30,292 square metres of floor space on the council-owned park-and-ride site off Eastern Avenue, which the council has agreed to sell to the developer.
  • Provision for a 49.9MW temporary energy centre, described in earlier reporting as gas-fired.
  • A long-term grid requirement of 150MW, which earlier BBC-sourced reporting said might not be delivered until between 2030 and 2034.

Context

The proposal has drawn sustained opposition over air quality, noise, flood risk, water use, carbon emissions and the loss of parking used by people travelling to the University Hospital of Wales. Plaid Cymru Senedd members Nick Carter and Zaynub Akbar, who requested the intervention, welcomed it, while stressing that the data centre had not been rejected. Local councillors also backed the call-in. Under the Welsh procedure, a planning inspector will examine the proposal and make recommendations before ministers take the final decision.

The 49.9MW figure sits just below the 50MW threshold above which energy generating stations in Wales need consent from the Welsh Government rather than the local authority. The Welsh Government has also said it intends to publish its own policy on data centres by the end of the year.

Why it matters for modular and edge in Europe

Cardiff East is a clear example of a model spreading across the UK and Europe: build now on temporary on-site gas generation, then switch to the grid years later. The call-in shows that this bridging approach can itself become the main planning risk, because it draws national energy and climate policy into what would otherwise be a local decision.

For developers of modular and edge capacity, the case points to the value of smaller, phased deployments that fit within available distribution-network capacity, avoid large standalone generation and can be located on sites with less community sensitivity. It also suggests that the forthcoming Welsh data centre policy, and similar rules elsewhere, will scrutinise power sourcing as closely as land use.

Sources


Discover more from DataCenters News

Subscribe to get the latest posts sent to your email.

Get DataCenters News by email

New stories on modular, containerised and edge data centres in Europe, straight to your inbox. No spam, unsubscribe at any time.

Leave a Reply