ENGIE and Google have signed a memorandum of understanding (MoU) on the energy supply for Google’s proposed data centre near Châteauroux in central France. Under the agreement, ENGIE could become Google’s preferred energy supplier and management partner for the site, although that depends on further agreements and on the project itself going ahead.
What the MoU covers
The French utility announced the agreement on 13 November. It sets out three areas of study rather than firm commitments: no electricity volumes, prices or timetable have been published.
- New clean generation: the companies will look at a large, multi-technology clean energy portfolio, including national-level renewable supply arrangements, designed so that the extra capacity does not raise power prices for French households or businesses.
- Grid support: they will assess grid integration and flexibility options, including utility-scale and behind-the-meter battery energy storage systems (BESS).
- Local affordability: they will explore energy-efficiency programmes for homes and buildings, local infrastructure such as electric mobility, and whether the data centre’s waste heat could be supplied free of charge to local district heating networks or other heat users.
ENGIE said it would contribute technical and energy expertise to the feasibility discussions. If the project proceeds, the solutions identified could then be developed further for implementation.
The project and its consultation
The proposed campus would sit in the Ozans business park in Étrechet, east of Châteauroux, on land of around 195 hectares that Châteauroux Métropole agreed to sell to a Google subsidiary. It would be Google’s first self-owned data centre in France. Google France, its subsidiaries Tricolore Computing and Violet Computing, and grid operator RTE, which is responsible for the high-voltage connection, referred the project to France’s National Commission for Public Debate (CNDP) in March. A preliminary public consultation opened on 2 November and runs until 10 January 2027.
The scheme has met local resistance. A residents’ petition calling for it to be dropped has gathered thousands of signatures, and several councillors in Étrechet, including the mayor, resigned in protest at how the project has been handled.
The MoU extends a relationship that began in 2021, when the two companies launched Europe’s first Carbon-Free Energy Manager model in Germany. Their partnership has since covered clean energy deals in Germany, Belgium, the UK and the US.
Why it matters for modular and edge in Europe
Châteauroux is a hyperscale project, but the terms being discussed are becoming a template that smaller operators will also be measured against. Commitments that new demand will not raise local power prices, on-site batteries that support the grid and heat given free to local networks are now part of the planning case in several European markets. France already requires data centres of at least 1MW to recover waste heat under certain conditions, so heat reuse is moving from good practice towards an expectation.
For modular and edge developers, that points to designing heat-recovery interfaces and battery integration into standard units from the start, and to forming utility partnerships early, as large players are now doing at the consultation stage.