Pace DC, the data centre arm of UK clean energy developer Pathfinder Clean Energy, is consulting on a four-building data centre campus north of Bedford that would draw power directly from an adjacent solar farm and battery storage scheme. The company held a public consultation event on 18 November and plans to submit a planning application later this year.
What is proposed
The Thurleigh Road Data Centre would sit on around 22 hectares of land off Thurleigh Road, between the villages of Milton Ernest and Thurleigh in Bedfordshire. According to the project website, the facility would connect directly to the already consented Thurleigh Road solar farm and battery energy storage system (BESS), so that locally generated renewable electricity can be used on site and reliance on the wider network is reduced.
Pace DC says the campus would use a closed-loop cooling system with no ongoing water consumption for cooling, and that it is exploring ways to reuse waste heat through a local heat network. It is targeting a minimum BREEAM Excellent rating and at least 10% biodiversity net gain on the site. The company has not published an IT capacity figure for the campus in its consultation materials.
Key figures and timeline
- Four buildings on roughly 22 hectares, according to a site plan reported by DatacenterDynamics.
- Planning application expected later in 2026, with Pace DC hoping for a decision by summer 2027.
- Estimated £2.5m–£3.5m a year in business rates for Bedford Borough Council, up to 1,500 direct construction jobs and around 80 full-time operational roles. Pace DC says these numbers will be refined in an economic impact assessment.
- Pace DC reports a UK pipeline of 186MW of IT capacity across eight sites, plus 160MW in New Zealand, with its first projects due online in 2028.
Who is behind it
Pathfinder Clean Energy (PACE) was founded in 2017 and says it has developed more than 2GW of clean energy infrastructure since then. Its data centre division launched at the start of this year. The company’s stated approach is to plan renewable generation, storage and computing demand as a single system from the outset, rather than adding power solutions after a site is chosen. It says it intends to remain the long-term owner and operator of the Bedford campus.
The proposal is one of several new schemes emerging in the south and east of England. In West Sussex, Meridian One has set out pre-planning proposals for a phased, liquid-cooled campus of up to 100MW at Hickstead, which has drawn concerns from countryside group CPRE Sussex over pressure on local water and electricity supplies.
Why it matters for modular and edge in Europe
Grid access is the main bottleneck for new data centre capacity in Great Britain. Ofgem has estimated that around 315 data centre projects, totalling 73GW of demand, sit in the connection queue, well above the country’s peak electricity demand. Pairing compute with on-site or adjacent generation and storage is one of the few routes developers have to reduce dependence on that queue.
Solar output is variable, so schemes of this type still need a grid connection or other firm supply, but co-location can ease the size of the import a site needs and improve its sustainability case with planners and local communities. The model is also a natural fit for smaller, modular and edge deployments: factory-built halls and prefabricated power and cooling skids can be sized and phased to match what a renewable asset and its batteries can support, and placed at existing generation sites rather than in congested metro hubs.
Whether Thurleigh Road progresses will depend on the planning process and community response, but it adds to a growing list of energy-led data centre proposals across the UK.