Real estate adviser CBRE expects 255MW of new colocation capacity to be delivered in Milan across 2027 and 2028, enough to lift the Italian city above Dublin as Europe’s fifth-largest data centre market. The forecast, published on 16 November alongside CBRE’s third-quarter European figures, points to demand moving beyond the traditional core hubs as power becomes harder to secure.
What CBRE is forecasting
According to CBRE, the bulk of Milan’s 255MW pipeline is being designed for hyperscale cloud providers and neoclouds, the GPU-focused cloud operators that have become a major source of AI demand. The firm links the requirement to hyperscalers expanding their cloud regions and accelerating AI programmes across Europe.
At the end of the third quarter of 2026, Milan and Dublin were separated by around 100MW of operational capacity. If the pipeline is delivered as planned, Milan would move ahead of the Irish capital in 2028. Much of the construction is taking place to the west of the city, with further large projects in Siziano and elsewhere in the metropolitan area.
Andrew Jay, CBRE’s head of data centre solutions for Europe, described the trend as marking the city’s “transition from a secondary market into a top European data centre hub”, and tied it to a wider shift of activity towards Southern Europe.
The numbers behind the shift
- Italy’s colocation market has grown roughly sixfold since 2020, driven by international operators building large facilities for hyperscale customers.
- Supply growth in Dublin has slowed in four of the five years since a de facto moratorium on new data centre grid connections took effect in late 2021.
- Vacancy across Frankfurt, London, Amsterdam, Paris and Dublin (FLAPD) fell to a record low of 5.8% in the third quarter, 2.2 percentage points lower than in the second.
- CBRE expects the overall European vacancy rate to end 2026 at 10.3%, more than two percentage points below the 2025 level.
DatacenterDynamics, reporting on the same figures, said Milan also recorded the highest take-up of the ten secondary markets CBRE tracks, a group that includes Berlin, Madrid, Munich, Stockholm, Warsaw and Zurich.
Constraints and caveats
CBRE notes that growth is continuing despite mounting power constraints in parts of the region, where grid connection lead times are lengthening. Kevin Restivo, the firm’s head of data centre research for Europe, cautioned that the speed of expansion needs close monitoring, particularly absorption rates and pre-leasing, so that supply does not run ahead of demand over the medium term.
Local acceptance is another factor. Earlier this month thousands of people gathered in Milan to protest against data centre expansion and called for a review of Lombardy’s recently adopted data centre law, according to DatacenterDynamics.
Why it matters for modular and edge in Europe
Milan’s rise is mainly a hyperscale story, but the conditions behind it are relevant to smaller and faster-to-deploy capacity. Record-low vacancy in the FLAPD hubs and longer connection queues push customers towards any metro where power can be secured, and secondary cities are absorbing that demand.
In that environment, capacity that can be added in increments as power becomes available, such as prefabricated power and cooling modules or containerised halls, gives developers a way to bring megawatts online in phases rather than waiting for a full campus. Growing metros like Milan also need regional and edge facilities for latency-sensitive services and AI inference, which tend to be smaller and closer to users than the hyperscale campuses that dominate CBRE’s pipeline.
The caution from CBRE’s own research team is a reminder that the opportunity depends on demand keeping pace with a fast-growing supply pipeline.
Sources
- CBRE – Milan set to become a top five European data centre market in 2028 (16 November 2026)
- CBRE – European Data Centres Figures Q3 2026
- DatacenterDynamics – CBRE: Milan set to overtake Dublin as fifth-largest data center market in Europe by 2028
- Baxtel – CBRE forecasts Milan will add 255MW and pass Dublin as Europe’s fifth market




Leave a Reply